The ceremony took place with key personnel from HHI, DNV and NOV present, along with the Deep Sea Metro (DSM) site team. This is a huge milestone for the team and for Odfjell Drilling.
The progress on DSM I is on schedule and the DSM site team are working closely with HHI to deliver a quality product.
What's next?
The next milestone for the DSM Site team will be the steel cutting commencement on DSM II, scheduled for 10th May 2010. There after DSM I will be launched in August 2010 to conclude outfitting at the quayside.
Read more: Odfjell Drilling's newbuild programme