On the 19th April the official keel laying ceremony took place for Deepsea Metro I.

The ceremony took place with key personnel from HHI, DNV and NOV present, along with the Deep Sea Metro (DSM) site team. This is a huge milestone for the team and for Odfjell Drilling.

The progress on DSM I is on schedule and the DSM site team are working closely with HHI to deliver a quality product.

What's next?
The next milestone for the DSM Site team will be the steel cutting commencement on DSM II, scheduled for 10th May 2010. There after DSM I will be launched in August 2010 to conclude outfitting at the quayside.

Read more: Odfjell Drilling's newbuild programme


Published: 28.04.2010